je dunn construction master logo
Thought Leadership
Healthcare
Phoenix

Ahead of the Game: Leveraging Procurement to Keep Project Schedules Intact

Long and unpredictable lead times, a lagging supply chain, and material shortages—compounded by recent escalation—are creating a new set of challenges for construction teams across the country. From budget and project planning all the way to breaking ground and ultimately ribbon cutting, the ripple effect of these factors is felt in all aspects of the construction process.

To retain the predictability and accuracy clients need, it’s the behind-the-scenes, up-front work and collaboration that can have a substantial impact on achieving project goals. While it’s not always front and center, leveraging procurement is a crucial piece of not only getting projects off the ground, but also in setting each one up for success.

Staying Ahead

The importance of swift decisions and sound processes—in addition to remaining adaptable—are essential in a time when trade partners cannot guarantee pricing over 90 days and lead times have swelled in some cases to 6 months. To combat the issues and avoid delays that could impact the overall project schedule, the team took a proactive approach to identify items with long lead times, allowing all parties to plan accordingly within the project schedule.

For this project, below are all the items we identified to secure preauthorization from the owner to begin procurement of these long lead items ahead of the main contract execution. Once the trades were cut loose on early procurement, we   worked closely with the reps to get their submittals in.

  • Structural Steel
  • Steel Decking
  • AHU
  • Cooling Towers
  • VAVs
  • VFDS
  • Chillers
  • Switchgear
  • UPS System
  • Generators
  • Transfer Switches
  • Light Fixtures
  • Structural steel
  • Major Mechanical/plumbing equipment
  • Major electrical equipment

 

In addition to identifying potential delays and prioritizing those items, trade partner buy-in and early submittals are critical to starting construction on time. By identifying long lead items that are critical to construction, we got the ball rolling on submittal development and submittal reviews and expedited the release for fabrication ASAP. We were experiencing a factory workforce shortage on our air handling units, which caused a one-month slip. If they weren’t in the fabrication que, this could’ve been a substantial delay.

Process Improvements

Recent delays and uncertainty caused by the current landscape have forced teams to get creative in their processes and adjust them to account for potential issues. Improvements in the procurement process at TMC Rincon include:

  • Utilizing a submittal party
    • Identify priority submittals with trade partners, followed by outreach to vendors on lead times to provide JE Dunn a list of critical items that needed to be released for production ASAP.
    • Request priority / long lead submittals from Trade Partners and notify design team of its priority.
    • Schedule meetings around 5-10 business days after submission that included JE Dunn, Design reviewers, Trade Partner, and vendor/manufacturer rep. Design team comes to the meeting with comments ready. Design reviewer goes through all the comments with the rep. The rep answers as many questions as possible and follows up with the factory on any comments that can’t be addressed right away.
    • Distribution – JE Dunn distributes the review back to trade partner and confirms receipt and follows up after a week or so with an estimated ship date.

 

  • Color-coded procurement log
    • This JE Dunn procurement log takes the P6 schedule data and creates a color-coded priority list. You assign each item to an activity on the schedule, and it helps back track the days you need submittal approval by. With built-in formulas and color coding, any item overdue automatically populates in red to easily flag potential delays for the team.

 

The Results

In short-term, the goal was to avoid potential delays caused by interruptions in the supply chain—but what the team did not realize at the time is just how impactful those decisions would end up being in the long-term due to (still) increasing escalation and inflation. We were able to lock in long-lead equipment orders into the factories to avoid longer disruptions and save costs. Our AHUs slipped an entire month due to a manpower shortage at the factory; if we had not gotten a preauthorization, our AHU would have slipped significantly and jeopardized the project schedule.

Going Forward

While project teams have adjusted to the changing procurement issues, the fact remains that no one can predict how long these challenges will persist. Though it’s been difficult at times, the benefits of evolving to tackle these issues will only improve future processes and create more efficiencies going forward. “Having an efficient, proven procurement process in place is beneficial to everyone involved in each project,” said Procurement Director Jason Banks. “In addition to helping head off delays in the field and keeping work moving the pace required by the schedule, it also creates a team atmosphere from top to bottom to increase transparency and engagement across the board.”

Ethan Schneider
Senior Project Engineer

related headlines

Projects
Healthcare
Atlanta
Wellstar Kennestone Hospital
Tower Addition
Wellstar Health System
Marietta, GA
Projects
Healthcare
Des Moines Kansas City
University of Iowa Hospitals & Clinics Forevergreen Road
University of Iowa Hospitals & Clinics
North Liberty, IA
Projects
Healthcare
Tampa
Tampa General Health Behavioral Health Hospital
LifePoint Health / Tampa General Hospital
Tampa, FL
Projects
Healthcare
Denver
West Pines Behavioral Health Hospital
Intermountain Health / Acadia Healthcare
Westminster, CO
Projects
Healthcare
Nashville
Williamson Health
ED Expansion & Renovation
Williamson Health
Franklin, TN
Projects
Healthcare
Atlanta
Wellstar Kennestone Hospital
Tower Addition
Wellstar Health System
Marietta, GA
Projects
Healthcare
Des Moines Kansas City
University of Iowa Hospitals & Clinics Forevergreen Road
University of Iowa Hospitals & Clinics
North Liberty, IA
Projects
Healthcare
Tampa
Tampa General Health Behavioral Health Hospital
LifePoint Health / Tampa General Hospital
Tampa, FL
Projects
Healthcare
Denver
West Pines Behavioral Health Hospital
Intermountain Health / Acadia Healthcare
Westminster, CO
Projects
Healthcare
Nashville
Williamson Health
ED Expansion & Renovation
Williamson Health
Franklin, TN
Projects
Healthcare
Denver
Rose Medical Center
Rose Medical Center / HCA Healthcare
Denver, CO
Projects
Healthcare
Atlanta
Northeast Georgia Health System
Lumpkin County Replacement Hospital
Northeast Georgia Medical Center
Dahlonega, GA
Projects
Federal Healthcare
Kansas City
Fort Leonard Wood
Hospital Replacement
U.S. Army Corps of Engineers Kansas City District
Fort Leonard Wood, Missouri
Projects
Healthcare
Austin
University Health System
Women's & Children's Tower & Parking Garage
University Health System
San Antonio, TX
Projects
Multi-Family, Student Housing & Senior Living
Phoenix
Moontower Phoenix
LV Collective
Phoenix, AZ
Projects
Healthcare
Denver
HCA Swedish Medical Center
Tower Expansion
HCA Healthcare
Englewood, CO
Projects
Healthcare
Portland
PeaceHealth St. John Medical Center 8th Floor Renovation
PeaceHealth
Longview, WA
Projects
Healthcare
Dickinson Kansas City Williston
Trinity Health Regional Healthcare Campus
Trinity Health
Minot, ND
Safety
Culture
Phoenix
Bringing Safety Culture to New Heights
Clay Creaser
Office Leader
Phoenix
May 2023
Women in Construction Week
Campaigns
Healthcare
Nashville
HCA Southern Hills Medical Center Operating Room Renovation
March 2023
Ethan Schneider
Senior Project Engineer
No data was found